PORT OF NEWCASTLE

Dust Controlled Hopper/Grab Solution

In 2018 Page Macrae Engineering was contracted to supply two new eco-hoppers and two mechanical chain grabs to the Port of Newcastle.

Used for the unloading of a variety of products including phosphate, fertiliser and animal feed, the hopper and grab solution has provided an interim measure to replace an ageing gantry system and to meet the environmental compliance requirements.

Despite their much smaller size, the eco-hopper/grab combination has a similar throughput per hour to the gantry-based system. The grabs having a larger capacity than the gantry-based grabs.

The result has been a huge reduction in dust levels on their most difficult product because of minimised spillage from the grabs and a high level of dust suppressed by the hoppers.

The eco-hopper and grab solution has proven itself in multiple ports throughout Australia since its introduction in 2010, meaning a much cleaner port environment and maximised productivity where they have been installed.

Project Commenced
November 2017
Project Ended
May 2018
Category
Port Equipment

Work Scope

  • Design 
  • Port Equipment
  • Quality Assurance
  • Commissioning, training and technical support

APM TERMINALS - PORT OF CALLAO, PERU

Dust Controlled Hoppers – Enviro-Max 50e

Three large dust control discharge hoppers destined for Port of Callao, Lima, Peru were shipped from Port of Tauranga. This was a first for the company with this export into the South American market.

Approached by a former Australian client now working in Peru, Page Macrae Engineering was awarded the contract for the hoppers in September 2016 and construction of three 41 tonne units, was completed in March 2017. The company’s standard design hoppers were customised to suit the lower than normal wharf load capacity.

The three hoppers were delivered to the Port of Tauranga in two sections and assembled as complete units on the wharf for transport on the deck of a specialist heavy-lift ship.

A client representative arrived in New Zealand to inspect the hoppers before they left on their 3-week voyage to Peru.  Two engineers from Page Macrae Engineering travelled to Lima to commission the hoppers and train the local operators.

Project Commenced
September 2016
Project Ended
March 2017
Category
Dust Controlled Hoppers
Commentary

“We were very excited by the opportunity to export into this new market. The hoppers were unique due to their lower than normal overall height and their wheel set system, which allowed the client to tow them into place and have them up and running in a matter of minutes. Commissioning the project in Peru brought its own set of challenges, such as the language barrier, which we took in our stride once we got there.

The customised hoppers were designed, developed and fabricated to be efficient, protect the environment from dust and spillage and meet the unique requirements of the client, load and port. Our team of engineers and designers were excited by the experience and opportunities that may arise in the future.”

Bruce Ennis  |  Manager  |  Product Development  |  Page Macrae Engineering

Work Scope

  • Design
  • Manufacture and export
  • Commissioning
  • Training and technical support

Sun Metals Corporation - Townsville, Australia

Dust Controlled Hopper – Enviro-Max 70

The Enviro-Max 70 Hopper, built for Sun Metals in Townsville, was unique in that it was specially designed to facilitate the unloading of zinc concentrate for transport to their plant while also being capable of loading ships with zinc ferrite for export.

The project brought a number of challenges for the company: The hopper needed to eliminate dust emissions, the product itself was sensitive to compaction and did not flow well and an extremely tight delivery deadline was also required.

Awarded the project in January 2016, Page Macrae Engineering engaged the services of a specialist consultant to carry out flow testing on the zinc product and report on handling difficulties. The result of the findings determined that a radical new approach to the design was required. The design called for a larger than normal hopper opening to achieve flow and to transfer the product to the truck a unique batch loading process was required. The end result, filling of a 90-tonne triple trailer road train in under 10 minutes.

In order to meet local dust suppression regulations, the truck filling operation was enclosed and fitted with a dust extractor and self-cleaning filter system. This enabled the hopper to maintain negative air pressure inside the enclosure preventing dust from escaping as well as dust suppression at the grizzly.

The 220-tonne unit was completed in October 2017 and shipped to Townsville for commissioning.

The system was successfully tested and commissioned and is now fully operational.

Project Commenced
January 2016
Project Ended
October 2016
Category
Dust Controlled Hoppers

Work Scope

  • Design and development
  • Manufacture and export
  • Commissioning
  • Training and technical support

QUBE - P&O AUTOMOTIVE & GENERAL STEVEDORING

Dust Controlled Eco-Hopper/Diesel-hydraulic Grab Solution

2010 saw the introduction of a new era in discharge hopper and grab technology.

Page Macrae Engineering was tasked with providing a solution for POAGS (now known as QUBE) Darwin operation. The client needed to comply with strict environmental standards being introduced around dust emissions. As the port shared the harbour and waterways with recreational users, they needed to ensure they did not damage the resource.

We undertook a major research and development project to deliver on both the customers and environmental requirements. The result, a newly designed and built eco-hopper and grab solution designed to minimize dust emissions while maximizing productivity.

The hoppers provided the vital link between removing bulk cargo from the ship’s hold and discharging into the waiting trucks as swiftly as possible. Special discharge spouts automatically adjusted according to the height of the load in the waiting truck, containing dust in the hopper rather than losing it to the atmosphere.

Three newly designed diesel hydraulic bulk grabs were supplied as part of the package and incorporated the dust sealing and mobile remote-control technology.

Project Commenced
2010
Project Ended
2010
Category
Dust Controlled Hoppers
Diesel Hydraulic Grabs

Work Scope

  • Design and development
  • Manufacture and export
  • Commissioning
  • Training and technical support

KONIAMBO NICKEL, NEW CALEDONIA

Diesel-hydraulic Grabs

In 2010, Page Macrae Engineering delivered four, 14 cubic metre bulk discharge diesel-hydraulic grabs to the enormous Koniambo nickel project in New Caledonia.

In 2010, Page Macrae Engineering delivered four, 14 cubic metre bulk discharge diesel-hydraulic grabs to the enormous Koniambo nickel project in New Caledonia. The project was a joint venture between the New Caledonian development agency and mineral company Xstrata Nickel. Xstrata will extract some 380 million tonnes of saprolite over the mine’s 50-year lifespan.

The remote coastal peninsula location, preservation of wetland, waterway and marine environments, were requirements of the mining company. Efficient use of energy, protection of natural resources, waste minimisation and biodiversity conservation were mandates for the project.

“The specifications for the project were very tight around our client’s expectations around noise and dust emissions from grab operation. We spent many hours designing and developing some new technology to incorporate into these grabs that is standard throughout the diesel-hydraulic range now,” said Port Equipment Manager, Bruce Ennis.

The Koniambo project also required equipment that did not compromise on productivity. The compact profile of the grabs and low drift profile suited the deep channel loading facility.

Downtime and maintenance minimisation were critical parameters. The grabs were fitted with diagnostic systems to ensure diagnosis was kept simple enabling faults to be fixed quickly. Building the power plant into the own sliding subframe module ensured the engine could be easily removed for servicing and testing. It also enabled a lower centre of gravity through the grab.

The Koniambo project marked a significant shift in grab design thinking and resulted in a major research and development project into productivity and environmental sensitivity.

Commentary

“We’ve proven that we can demonstrate genuine research, development, design and manufacture capability, backed up by technical support, service and parts for our equipment,” says Bruce Ennis, “Page Macrae Engineering now focuses on the whole chain and life cycle bulk handling solutions. Our equipment now includes both wire and chain, mechanical and diesel-hydraulic bulk grabs for ship unloading. Teamed with our Enviro-Max Hoppers, these are a proven solution for discharging cleanly and efficiently with technology ensuring productivity, environmental, health and safety requirements are being met.”

Bruce Ennis  |  Manager  |  Product Development  |  Page Macrae Engineering

Project Commenced
2010
Project Ended
2012
Category
Diesel Hydraulic Grabs

Work Scope

  • Design and development
  • Manufacture and export
  • Commissioning
  • Training and technical support
keyboard_arrow_up